WATCH AS WE PROGRESS WITH OUR NEW MINISTRY EXPANSION 


ADDING THE TRUSSES  ~ October 14-18th 


FRAMING THE ROOMS ~ September 23 – October 4


WE HAVE OUTSIDE WALLS  ~ September 25 & 26


POURING FOR A FIRM FOUNDATION ~ September 24th


DIGGING THE WATER & SEWER LINES ~ SEPTEMBER 22-23rd


UNDERGROUND PLUMBING ~ SEPTEMBER 9th – 20th


POURING THE FOOTER WALLS ~ SEPTEMBER 2nd – 6th


PREPARING THE FOOTER WALLS ~ AUGUST 26th – 30th


DIGGING & TRENCHING THE WEEK OF AUGUST 19TH


CORNERSTONE @ WORK WEEK OF AUGUST 12TH


EXCAVATING AUGUST 5-9


EXCAVATING JULY 22 – JULY 31, 2019


THE TRUCKS ARRIVED THE WEEK OF JULY 15, 2019


GROUND BREAKING JUNE 2, 2019